6.3.1 PERT technique continued

Using the formula for  Te= (a+4m+b)/6 and σ2= (ba/6)2, the estimated times and variances are completed as shown in the this table.

Activity

Predecessor

a

m

b

Expected Time

Variance

A

6

7

14

8

1.78

B

8

10

12

10

0.44

C

A

2

3

4

3

0.11

D

A

6

7

8

7

0.11

E

B,C

5

5.5

9

6

0.44

F

B,C

5

7

9

7

0.44

G

D,E

4

6

8

6

0.44

H

F

2.5

3

3.5

3

0.03

We can now determine the completion time and critical path as before. The answer is shown herepert-techniquex

From the network diagram, the estimated project completion time is 23 weeks

Verify for yourself that the critical path is A, C,E, G. See diagram here pert-technique-with-cpx

This means we have a 50% probability of completing the project in 23 weeks or less.