8-4.2 Earned Value Analysis- 2nd example

Here is another example

1.       At the end of week 5, Project KZNN has cost $60,000 and has an earned value as indicated in the table. Use the data to calculate the cost variance, cost performance index, the schedule variance, schedule performance index, the time variance, critical ratio, the estimate at completion, the budget at completion for the project. All amounts are in thousands of dollars. The solution to this problem is shown on the next page.

 

Duration

Budget

Predecessor

% Comp
Conceptual Design (A)

2

20

 

100%
Graphics Design (B)

3

22

 

80%
Copyright (C)

3

15

B

 
Samples (D)

2

6

A

100%
Tooling (E)

3

18

D

67%
Production (F)

3

22

E

 

Leave a Reply